The folllowing road projects are scheduled for the summer of 2017:

  • North Bridge Drive.  Milling and paving to begin on July 27 and last for approximately 2 weeks. Paving scheduled for August 16. 
  • West Springtown Road (Schooley's Mtn Rd to Wehrli Dr.).  Milling and Paving to begin July 14 and end by July 31. Paving scheduled to begin 7/26, 7:30 am - 7:30 pm
  • Spruce Lane. Starting on or about July 31 for approximately 10 days. Driveways will be inaccessible on Spruce Lane for 2 days during milling, and on Dogwood for 1 day.  Notices will be provided by contractor day prior.  Work will be done by American Asphalt & Milling, Kearny NJ. Paving scheduled for August 16
  • Naughright Road (Flocktown Rd to Fawnridge Dr).  Scheduled to begin August 7. Paving scheduled to take place August 17
  • Naughright Road (Ranney to Fairview). Completed.
  • East Fox Hill, Black River and Hacklebarney Road.  Portions of each will be paved by the DPW this summer.
  • Fairview Ave.  The DPW will be applying oil & chip to portions of upper and lower Fairview Ave. Completed
  • Laketown Road.  The DPW will be applying oil & chip to all of Laketown Road. Completed
  • Portions of Wherli and Califon roads. The DPW will be applying oil & chip this summer.

The County will be paving a portion of Fairmount Road (from West Mill to Highland)  scheduled to begin Aug 28.  Visit the County website for more details.  

 

Please continue to check the website for updates throughout the summer. 